For several years our district looked for solutions to address our facility issues which include classroom and common space overcrowding, ADA accessibility, building security, and our ability to support modern learning. In January 2019 our Board of Education voted 7-0 to place a facilities referendum question on the April election ballot. The question was designed to address the district's previously identified facilities needs. On April 2, 2019, the School District of Milton voters approved a $59.9 million referendum for additions and renovations to nearly every school. The goal of the referendum was, and continues to be, to help provide safe and quality educational experiences for our students.
East Addition Progress - Photo taken 2.5.20
West Addition Progress - Photo taken 2.5.20
Harmony Addition Progress - Photo taken 2.5.20
Milton High School Addition Progress - 4.5.21
Huffman Facility Development, Inc.
"The mission of Huffman Facility Development is to assist clients in the development of their construction projects, with a consistent focus on the creation of spaces that fully meet the end users' functional needs and aesthetic concerns. In connection with this primary focus, we work to promote a fair, honest, team-oriented development process and actively seek projects that offer socially redeeming value to the larger community."
The board of education contracted with Huffman Facility Development to act as the districts owners' representative through the design, bidding, and construction phasing of the $59.9 facilities referendum. As part of the Huffman Facility Development services, they provide a monthly progress report on all phases of the ongoing projects. This written report is provided to the board on the second board meeting of each month.
Project Status Report | June 10 - July 15
Project Status Report | August 1 - August 23
Project Status Report | August 26 - September 23
Project Status Report | September 23 - October 24
Project Status Report | October 24 - November 21
Project Status Report | November 21 - December 20
Project Status Report | December 20 - January 24
Project Status Report | January 24 - February 20
Project Status Report | March 20
Project Status Report | April 27
Project Status Report | May 22
Project Status Report | June 18
Project Status Report | July 22
Project Status Report | August 20
Project Status Report | September 24
Project Status Report | October 26
Project Status Report | November 23
Project Status Report | December 31
Project Status Report | January 25
Design & Construction
Schematic Design
Milton East Elementary - Board of Education approved 6.24.19
Milton West Elementary - Board of Education approved 6.24.19
Harmony Elementary - Board of Education approved 6.24.19
Consolidated Elementary - Board of Education approved 6.24.19
Milton Middle School - Board of Education approved 8.12.19
Milton High School - Board of Education approved 10.28.19
Design Development
Milton East Elementary - Board of Education approved 8.12.19
Milton West Elementary - Board of Education approved 8.12.19
Harmony Elementary - Board of Education approved 8.12.19
Consolidated Elementary - Board of Education approved 8.12.19
Milton Middle School - Board of Education approved 11.25.19
Milton High School - Board of Education approved 1.13.20
Construction Documents
Milton East Elementary - Bid Due Date 10.8.19 2pm
Milton West Elementary - Bid Due Date 10.8.19 2pm
Harmony Elementary - Bid Due Date 10.8.19 2pm
Consolidated Elementary - Bid Due Date 10.8.19 2pm
Milton Middle School* - Bid Due Date 3.10.20 2pm
Milton High School* - Bid Due Date 4.9.20 2pm